Alaska workforce camp bid risk review

A worked example for estimating teams comparing ramp-up, steady operations, and demobilization.

Establish the man-day basis

One man-day represents one resident served for one day in this example. Confirm the contract’s counting rule for arrival and departure days, vacancies, and visitor meals. Reconcile daily counts to the monthly invoice.

Illustrative 30-day month at 80% average occupancy
Installed bedsAverage residentsMonthly man-days
120962,880
3002407,200
60048014,400
90072021,600
1,10088026,400

Test the occupancy exposure

At 1,100 beds, a drop from 80% to 60% occupancy reduces the month from 26,400 to 19,800 man-days. Each $100,000 of fixed monthly expense contributes $3.79 per man-day at 80% and $5.05 at 60%. The $100,000 is an illustrative cost block, not a quoted operating budget.

Calculate operating cost per man-day by dividing fixed operating costs plus volume-driven expenses by forecast man-days for the same period. Price one-time moves, separately reimbursable items, and commercial margin according to the tender schedule.

Put competing maintenance offers on the same basis

Illustrative example for a 300-bed camp averaging 240 residents over 30 days, or 7,200 man-days. Assume equivalent response times and service coverage after the exclusions below are priced. The figures are fictional.

Monthly maintenance comparison in US dollars
Cost itemProvider AProvider B
Quoted monthly fee$78,000$92,000
Call-out labor and travel$10,000 allowanceIncluded
Parts and freight$9,000 allowanceIncluded
Evaluated monthly cost$97,000$92,000
Maintenance cost per man-day$13.47$12.78

Provider A starts $14,000 lower. Once its excluded costs exceed $14,000 for the month, Provider B costs less under these assumptions. In the illustrated case the difference is $5,000. Obtain written confirmation of parts limits, travel coverage, and response times before relying on either price.

Decision for the bid room

Have the maintenance lead confirm the asset list and required coverage. Have procurement obtain written answers from both providers. Have the bid lead carry any unresolved allowance into the commercial offer and identify who pays if actual costs exceed it.

Resolve these items before pricing closes

Maintenance

Confirm the asset register, inspection intervals, trade call-outs, and who owns major overhaul costs. Reconcile tools and vehicle upkeep against equipment rates to avoid double counting.

Transportation

Map scheduled crew changes and shuttle runs by leg. Run a weather hold with extra paid hours, lodging, and rebooking. Record the trigger and payer for standby.

Freight

Reprice a missed scheduled delivery using emergency air transport. Separate the carrier charge, fuel surcharge, consolidation, and cold-chain handling. Check whether the client reimburses any premium.

Commercial decision

Obtain a minimum staffing or occupancy commitment, or submit a tiered rate. Record each unresolved issue, its pricing treatment, its owner, and the clarification deadline.